Bay Developments: As a trust port, Peterhead Port Authority reinvests
all of its profit into Peterhead Bay and Harbour. During
recent years several major capital investments have been
made. The proven track record of making strategic
investments to secure the long-term future of the port
will be maintained in coming years. Recent investments
and those which will be completed by the end of the
century total over 8 million and include:
1993/4
Construction of Princess Royal Jetty providing 3
additional berths for oil related and bulk cargo vessels
in response to increasing traffic volumes.
Construction of Peterhead Bay Marina providing purpose
built facilities for the leisure sailor.
1996
Assisting ASCo with the provision of improved fendering
along the South Base Quay.
A trial section of wave wall, measuring 60 metres long
and 4 metres high was installed at the root of the North
Breakwater.
A new, enlarged control tower for provision of vessel
traffic advisory and Pilotage services was provided
jointly with Peterhead Harbour Trust.
Procurement of equipment to allow in-house seabed
surveys to be undertaken and results processed to
produce prompt production of depth charts in response to
clients' enquiries.
1997
Four Yokohama fenders were procured for deployment at
the North or South Breakwaters.
Berth 1 was dredged to 6.5 metres Chart Datum to
accommodate deeper draughted vessels.
1997/98
Expansion of Peterhead Bay Marina by provision of a
second protective breakwater and installation of
additional 58 pontoon berths - partly financed under the
European Union "PESCA" scheme.
1998
Joint provision with ASCo of an additional 2,500 tonne
capacity fresh after storage tank and upgraded delivery
system to improve vessel bunkering rates at the South
Base Quay and Princess Royal Jetty. This investment
ensures that those vessels requiring large volumes of
fresh water are not delayed due to reduced loading rates
which previously occurred when several vessels were
loading simultaneously.
1998/99
Construction of a protective wave wall along the seaward
edge of the North Breakwater in a £1.1 million
investment funded by the Authority with assistance from
a European Union "PESCA" grant. This structure has
historically been subject to closure during overtopping
seas. The trial section of wave wall will be extended
along the complete length of the structure. The wave
wall has been engineered to allow use of the large
capacity cranes for heavy lift operations. When complete
the wall will eliminate overtopping seas. This will
provide existing and potential clients with
significantly greater confidence that planned cargo
handling operations at the berths can be completed
without disruption caused by sea and swell conditions.
2001
Opening of fully chilled, purpose built 24 hour fish
market.
2006
Historic joining of Peterhead Harbour and Bay Authority
to become Peterhead Port Authority.
Peterhead fish landings total £107 million - highest
white fish and (for the first time) pelagic fish
landings in UK.
2007
Opening of new office extension at West Pier, Peterhead.
2008
Commence development of Smith Embankment Development; a
£32 million project to create a new 650ft quay and a
328ft breakwater extension to Albert Quay.